The Daily News gets its hands on an internal report excoriating the M.T.A. for poor maintenance and communications during the Sept. 8, 2004, flooding of subway tunnels. Among other issues:
Some TA “first responders” to flooding locations took more than an hour to arrive, and in some cases didn’t make it. Some had to rely on the subways – which were a mess.